Construction of photovoltaic power plants Laziska 1 and Laziska 2 in Poland

Construction work on the Laziska 1 and Laziska 2 photovoltaic power plants in Poland with a total capacity of 1.8 MWp is coming to a successful end. Works are 95 % completed.

At the both power plants, all the main components are already installed. 

The panels are mounted and interconnected to the inverters, earthing finished, the substation is built with the connected transformer, the fence with the access gates is built, the power output to the medium high voltage line is completed.

All that remains is to complete the low-voltage cable connection between the inverters and the transformer, the telemechanic system of the power plant and to install few elements of the power plant monitoring.